How to write a construction daily log that holds up
What to record every day, how to write it so it can’t be picked apart, and why the log you skip is the one you’ll need.
A daily log, or daily report, is the job’s diary: what happened on site today, written down today. Most contractors keep one. Fewer keep one that would help them in an argument.
When a job goes wrong, the log is often the only record made at the time. A claim for more time, a back-charge or an injury claim can turn on what it says about one day, months ago.
Here’s what to put in it, how to write it, and how to keep it up every day.
What goes in a daily log
Every log should answer the same questions in the same order, every day. A fixed order makes a missing part easy to spot.
- The date, the job and who wrote it. One log per job per day. The writer’s name is part of the record.
- Weather. Temperature, rain or snow and wind, with times if it changed. Say what it stopped, too: “No concrete placed, rain from 13:00.”
- Crew and hours. Your people by trade, and every sub by company and headcount. Note who arrived late or left early.
- Work done, by area. Where and how much: “Level 2 east, partitions framed from grid 3 to 6.” Not just “framing.”
- Deliveries. What came, from whom, and what was short, damaged or turned away.
- Visitors and inspections. The inspector, the engineer, the owner: who came, what they looked at, and what they said or passed.
- Delays and their cause. What stopped, when, for how long, who it held up and why.
- Instructions. Any direction given on site, and by whom, especially one that changes the work.
- Safety. The toolbox talk, any near miss or injury, and what was done about it.
- Photos. Taken that day and filed with the log.
Count the crew the same way every day, yours and the subs’, so the numbers can be added up later:
| Your carpenters, 4 at 8 hours | 32 hours |
|---|---|
| Your labourer, 1 at 6 hours (left at 13:00) | 6 hours |
| Electrical sub, 2 at 8 hours | 16 hours |
| Drywall sub, 3 at 4 hours (arrived 11:00) | 12 hours |
| On site, 10 people | 66 hours |
If a sub later bills for more time than this, or says their crew was on site when it wasn’t, the log is your answer.
Add the plan for the next day if it helps the next shift. Later, it also shows what you expected to happen beside what did.
Write facts, not opinions
A log is read later by someone who wasn’t there, often someone looking for a weak spot. Write it so every line could be checked.
- Say what you saw, not what you think. “Drywall sub had 2 people on site, 4 expected” holds up. “Drywall sub is useless” doesn’t.
- Use numbers and times. “Pump truck booked for 08:00, arrived 10:40” beats “pump was late.”
- Say where. The unit, the floor, the room or the grid line. “The basement” could be three places.
- Say who told you. “Owner’s rep asked us to hold the east wall” records an instruction. “East wall on hold” doesn’t say why.
- Leave out blame and feelings. No “as usual,” no “terrible,” no guesses at fault. If it matters, the facts will show it.
If you got something wrong, don’t rub it out. Add a dated note that corrects it. A log changed later with nothing to say so looks worse than the mistake did.
Write it the same day, every day
A log written at the end of the day is a record. One written on Friday for the whole week is a memory, and anyone arguing with you will say so.
Write it before you leave site, or once you’re parked on the way home. Five minutes then saves an hour of guessing later.
Write one every day the job is open, quiet days included. “No work on site, waiting on the window delivery” is the line that proves the wait.
Keep the logs in one place, by job and date, where the office can read them that night. A notebook in a truck helps nobody, and it gets lost.
Who writes it and who signs it
The person running the site writes the log: the super or the foreman. They saw the day. The office can tidy the wording, but never change the facts.
Put the writer’s name on every log. On bigger jobs, have the project manager read them each week, so a problem in one is caught while it can still be fixed.
If your contract asks for logs to go to the owner or the consultant, send them on time. A log they received at the time is hard for them to dispute later.
Check your contract and the rules where you work
Your contract may say what a log must hold, who signs it and when it goes to the owner. How long to keep job records, and how and when an injury must be reported, depend on your province or state and your insurer. Check before the job starts.
Why it matters in a dispute
Most construction disputes are about time and money: who caused the delay, what the extra work was, whether the work was done right. Each one turns on what happened on particular days.
A record made that day, by the person who was there, is hard to argue with. Memories a year later are easy to argue with. A gap in the logs is a gap in your side of the story.
The logs answer the questions you’ll be asked. When did the inspector pass the framing? How many days did rain stop the roof? Who told you to move the door?
When a day matters, a delay, an instruction or an injury, put it in the log and follow it up in writing to whoever needs to know. The guide to documenting a delay shows how.
How CrewLog does it
In CrewLog, the foreman talks through the day or types a few lines, and CrewLog writes the daily report. Or they fill in its sections themselves.
The sections are the same every time: work completed, delays, issues and follow-ups, deliveries, site conditions, safety, crew, and the plan for the next day. An empty one doesn’t print.
It writes only what was said. If the notes are too thin to write from, it asks for more instead of filling the gaps.
The day’s report, as CrewLog wrote it. Weather, crew and who logged it, the work done, and the extra it flagged for a change order.
Each report carries the date, the day’s weather at the job’s address, the crew on site and who logged it, with the photos attached. Other companies on site can be added with their headcount.
When CrewLog writes it, delays, delivery problems, possible extras and safety matters are flagged at the top, and follow-ups in the notes can become tasks on the job.
The report shows when it was created and when it was sent. Once it’s sent, only the owner or an admin can change or delete it. The foreman’s own notes stay with it, and the client never sees them.
No signal on site? The report saves on the phone and sends itself once there’s signal. Send it to the client by email, or as a link that opens with no login.
If your crew is on the Schedule or the time clock, the job’s page names the recent days someone was on site with no log. A reminder can come by email or on your phone at a time you set.