How to document a construction delay before it costs you
Give notice in writing and on time, keep the record every day the delay lasts, and treat time and money as two separate questions.
Every job gets delayed: rain, a late delivery, an inspector who doesn’t show, a design answer that takes three weeks.
Many of those delays aren’t yours, but you pay for them unless you can show what happened.
Getting more time or money for a delay usually takes two things: notice given the way your contract says, and a record of the cause and the cost. A good claim with neither is hard to win.
Here’s how to do both while the delay is happening, not months later.
Give notice in writing, and on time
Many contracts say you must give written notice of a delay, or of anything you think will cost more time or money, within a set time of knowing about it. Miss it and you can lose the claim.
Find the notice clause before the job starts. Write down how long you have, who notice goes to, and how it must be sent: email, letter, or a form of its own.
Then give notice as soon as you know, even if you don’t know the cost yet. Notice says “this is happening, and we may claim.” The numbers can follow.
Don’t rely on a phone call or a word at the site meeting. If it isn’t in writing to the person your contract names, it may not count.
Check your contract
How soon notice is due, who gets it and what it must say are set by your contract, and they differ from one contract to the next. Some are short. Read the clause before you need it.
What a delay notice should say
Keep it short and factual. A notice isn’t the place to argue about fault. It needs:
- What happened. The event, plainly: the steel didn’t arrive, the RFI wasn’t answered, the site flooded.
- The cause, as far as you know it. What you know, not what you suspect. If you don’t know yet, say so.
- When it started. The date, and the time if it matters. A delay with a known start is easier to count.
- What it affects. The work that can’t go ahead, the work that follows it, and whether it touches the finish date.
- What you’re doing about it. Moving the crew, changing the order of work, chasing the supplier.
- That you may claim. Say you reserve the right to claim more time and cost, with details to follow.
Here’s one, sent the day the delay started:
- Notice of delay, Harbourview: the level 2 slab.
- What happened: the answer to RFI‑021, on the new openings in the level 2 slab, was due Friday, November 13. It hasn’t come.
- Started: Monday, November 16. Rebar placing at the openings stopped at 10:00.
- Affected: the slab pour booked for Thursday, November 19, and the level 3 forming after it.
- What we’re doing: the crew has moved to the stair cores, and the pump is on hold.
- Claim: we reserve the right to claim more time and the costs of this delay. Details will follow.
Send it to the person your contract names, keep a copy, and note in that day’s log that it went. The RFI guide covers chasing the answer itself.
Keep the record every day it lasts
One notice at the start isn’t enough. A delay claim is built day by day from records made at the time. Every day the delay runs, the daily log should say:
- Whether the delay is still going, and what you’re waiting for.
- Who was on site, and what they did instead.
- Equipment standing idle, and rentals still running.
- Every call, email and meeting about it, with the date.
- The weather, when the weather is the cause.
Take photos the same way: the area that can’t go ahead, the missing material, the flooded trench, each dated and labelled. The site photos guide shows how.
Write down the day it ends, too. A delay with a clear start and finish is a number of days. One that just fades out is an argument.
Count what it costs you
While it’s happening, track what the delay costs you each day. You may not be able to claim all of it, but you can’t claim what you never recorded.
| Crew with no other work, 4 people, 8 hours at $60 | $1,920.00 |
|---|---|
| Scissor lift on rent, standing idle | $180.00 |
| Site trailer, toilets and bin, by the day | $95.00 |
| Supervision, 4 hours at $75 | $300.00 |
| One day’s cost, before markup | $2,495.00 |
Moving the crew to other work cuts the first line, and you should. What’s left is what the delay itself costs you each day.
Rentals, the trailer and supervision keep running whether anyone works or not. Those are the costs that get forgotten.
Price your people at what an hour really costs you, the wage plus its burden. The job costing guide shows how to work it out.
Time and money are separate questions
A delay raises two questions, and each one is answered on its own:
- More time: should the finish date move, so you aren’t charged for finishing late?
- More money: should you be paid for what the delay cost you?
You can be owed one without the other. Under many contracts, bad weather can earn more time but no money, because nobody caused it. A delay the owner caused may earn both.
Ask for each one plainly, with its own support: the days for the time, the costs for the money. When it’s agreed, get it into a signed change order, the new date and the price both.
The extras guide shows how to price a change order and get it signed.
This isn’t legal advice
Whether a delay earns time, money or both depends on your contract and the law where the job is. If a delay is long or the sum is large, talk to a construction lawyer early, while notice can still be given.
How CrewLog does it
In CrewLog, a delay goes in the daily report under Delays: when it started and stopped, how long it lasted, the cause as reported, who it held up and what was done.
CrewLog writes only what the foreman said, and it doesn’t assign fault the notes don’t state. The day’s weather at the job’s address goes on the report by itself.
Each delay is flagged on its report, and the job’s page counts the delays reported on it. Photos are filed by job and day, with any note you add.
The job’s page counts the delays reported on it. Four on this job, beside how far past its target it is.
Ask the Assistant what held up a job last month, and it reads that month’s daily logs to answer.
When more time or money is agreed, a change order carries it: the price, a line for the schedule impact, and the client’s signature, made on their phone.
CrewLog doesn’t write or send the notice of delay. Send that the way your contract says. Export the job as one folder, and every daily report is a PDF named by its date, beside the photos.
Daily reports, photos, the Assistant and the job folder are on every plan, from $39 a month. Change orders are on Crew at $89 a month and Pro at $179. Compare the plans.
More on daily reports, the Assistant and change orders on the features page.