How to build a two-week lookahead schedule

The next two or three weeks of the master schedule, broken into work a crew can do, with everything it waits on cleared first.

Field6 min readUpdated

A master schedule says when the job should finish. It’s planned in weeks and months, usually by the office, and it rarely says who is doing what next Tuesday.

A lookahead is the next two or three weeks of it, broken down into work a crew can do, with everything that work is waiting on checked first.

Built every week and gone through in a short meeting, it’s how your foremen and your subs agree on what happens next, and find the problems while there’s time to fix them.

What a lookahead is, next to the master schedule

The master schedule is the plan for the whole job: activities that run for weeks, like level 2 framing or mechanical rough-in, tied to the contract dates.

The lookahead takes the next stretch of it and turns each activity into tasks that fill a day or two: which area, which crew, how many people and what has to be there first.

How far ahead to look:

  • Two weeks suits most residential and small commercial work, where plans change fast.
  • Three weeks suits bigger jobs, with long lead items, inspections that need notice and more subs to line up.
  • Further out, the detail goes stale before you use it. Keep the longer view on the master schedule.

The lookahead doesn’t replace the master schedule, it feeds it. If the lookahead shows framing finishing a week late, the master schedule needs to hear about it this week.

Build it from the master schedule every week

Pick a day and keep to it. Building it on Thursday or Friday leaves time to send it out before the next week starts.

  1. Roll it forward a week. Drop the week that’s finished and add the next one from the master schedule, so you always see the same distance ahead.
  2. Break each activity into tasks. Level 2 framing becomes east walls Monday and Tuesday, west walls Wednesday, sheathing Thursday. A task should fit in a day or two.
  3. Name the area and the crew. Each task says where, like the floor, the unit or the grid lines, and who: your crew and how many, or which sub.
  4. Put inspections and deliveries on it. They’re tasks too, with dates that other work depends on.
  5. Check every task’s constraints. A task with something still missing isn’t ready, and it shouldn’t sit on next week’s plan as if it were.
  6. Hold it against the master schedule. If a task now lands past its date there, say so this week, not at the end of the month.

Keep it to a page per job, in the words your crew uses. A lookahead nobody can read on site is one nobody follows.

Clear the constraints before the work is due

A constraint is anything that has to be in place before a crew can start a task. Most lost days trace back to one of five:

  • Materials. Ordered, confirmed and on site, not “should ship this week”. Track long lead items from the day the order goes in.
  • Inspections. Booked with the notice your building department needs, and passed before anything covers the work up.
  • RFIs and submittals. An open question on the drawings, or a product not yet approved, holds the task until it’s answered.
  • Subs. Confirmed for the dates, with the crew size the task needs, and the area clear for them.
  • Your own crew and equipment. The right people, and the lift, the bin or the pump truck, booked for the day.

Your own crew, counted weeks ahead. The crew forecast puts the people your jobs need against the people you have: the week of Dec 14 is short one.

Give every open constraint an owner and a date it has to clear by, a few days ahead of the task. Check them every day, not once a week.

When one won’t clear in time, move the task before the crew shows up, and fill the gap with work that is ready.

The RFI guide and the submittal log guide show how to chase the two that wait on other people.

Run the weekly lookahead meeting

Once a week, on the same day, the people running the work go through the lookahead together: your foremen, each sub’s foreman and whoever orders the material.

  1. Start with last week. What was planned, what got done, and why anything didn’t. Facts, not blame.
  2. Go through the next two weeks, task by task. Each foreman confirms their dates, their crew size and what they need from everyone else.
  3. Go through the open constraints. Each one gets an owner and a date, said out loud in front of everyone.
  4. Sort out who works where. Two trades in one room on the same day is an argument on site and a lost day.
  5. Send it out the same day. The updated lookahead and the open items, to everyone who was there and anyone who wasn’t.

Keep it short. Half an hour that ends with names and dates beats an hour that ends with “we’ll see”.

Keep minutes, so the open items carry from one week to the next. The meeting minutes guide shows how.

Track what was planned against what got done

At the end of each week, go down last week’s tasks and mark each one done or not done. Done means finished, not mostly finished.

The share that got done is how reliable your plan is. It tells your crew and your subs how far they can trust next week’s.

Worked example: last week at Birchwood
Tasks planned for the week20
Done as planned16
Planned work done, 16 of 2080%

The four not done: two waited on the windows, one on the framing inspection and one on a change the client made. The windows were known to be late a week before.

Write down why each one wasn’t done: materials, an inspection, a sub, the weather, a change or your own crew. After a few weeks, the reasons show where your planning leaks.

Don’t aim for every task, every week. A plan that always gets done was padded. Aim for a number that climbs as the same reasons stop coming up.

Check your contract

If the lookahead shows work held up by the owner, the design team or another trade, your contract may require written notice of the delay within a set time. Find that clause before you need it.

How CrewLog does it

CrewLog’s Schedule is a desk calendar: Month, Week and Day, for every job or filtered to one.

Each day shows who is booked on which job, job starts and due dates, deliveries, RFIs on the day they’re due and anyone off, so what the work waits on sits beside the work.

Each delivery is entered as a material on the job, with its supplier, quantity and the date it’s needed. It’s marked ordered, confirmed or received, and one past its date is flagged.

An open constraint can be a task on the job, with the person who owns it and a due date.

The crew forecast counts the people your jobs need each week against the people you have, and its Worked row shows how many people logged hours on them that week, from the timesheets.

A job’s phases can carry their own dates, crew and how far along they are. A phase done by a subcontractor is named on its week and never counted as your people.

A trade meeting’s standard agenda has a section for the schedule and lookahead, and open items carry forward to the next meeting with their owners and due dates.

The Schedule, the crew forecast, tasks and meeting minutes are on Crew at $89 a month and Pro at $179. A job’s phases are on Pro at $179 a month. Compare the plans.

More on the Schedule on the features page.

More guides

All guides

Plan the next two weeks where everyone can see them.

Crews, deliveries and RFI due dates on one Schedule, and each week’s people against what your jobs need.

14 days free, no card to start. Then $39 to $179 a month for the whole company.