How to close out a construction job, from punch list to final payment

The deficiency walk, the hand-over, the final invoice and the holdback, in the order that gets you paid and remembered well.

Clients6 min readUpdated

The last few percent of a job takes longer than it should. The crew has moved on, small items drag, and the final payment and the holdback wait on all of it.

A clean close-out gets you paid sooner, ends the job on good terms, and leaves you a client who’ll recommend you. Here’s the order to do it in.

Walk the deficiency list

Before the client or the consultant walks the job, walk it yourself. Find your own deficiencies first: it’s faster, and it shows them a job that’s ready.

Then book the walk with the person who can sign off, and go room by room together. For each item, write down:

  • Where: the unit, the room, the wall.
  • What: “paint touch-up beside the light switch,” not “paint.”
  • Who fixes it: your crew, or which sub.
  • By when: a date, not “soon.”
  • A photo, so nobody argues later about what the item was.

At the end of the walk, ask them to agree the list is complete. A list that grows every week keeps a job open for months.

Watch for changes dressed up as deficiencies. An outlet nobody asked for before is an extra, not a fix. The extras guide shows how to price it.

Fix it and get it signed off

  1. Book the subs together. Give each trade its items and one date to come back. One visit each beats five.
  2. Fix what stops people using the space first. A door that won’t latch matters more than a scuff.
  3. Photograph each item fixed, from the same spot as the first photo.
  4. Clean before the last walk. Every surface dusted, windows done inside, floors cleaned, and your bins and leftovers off the site and the street.
  5. Walk it again with the client, and tick each item off together.
  6. Get the sign-off in writing: the list with every item marked done, signed or emailed back by the client.

If an item can’t be done yet, a part on backorder or work that waits for spring, put it on the list with a date. Don’t let one late part hold up the rest of the close-out.

Hand over the paperwork

The client should leave with everything they need to run, maintain and repair what you built. Gather it as the job goes, not in the last week:

  • As-built drawings, or drawings marked up to show what changed: where the pipes, wires and shut-offs really are.
  • Manuals and warranties for every product and piece of equipment you installed, with the model and serial numbers.
  • Your own warranty, in writing: what it covers, for how long, and how to reach you.
  • Permit and inspection sign-offs, and any certificates the job needed.
  • The finishes: paint colours, tile, fixtures and hardware, so they can match them later.
  • Keys, codes and spare materials. A box of leftover tile is worth more to them than you’d think.
  • Photos of what’s inside the walls.

Put it all in one folder with a contents page, hand it over in person if you can, and keep a full copy yourself.

Send the final invoice and release the holdback

Send the final invoice as soon as the work it bills is done. Check your contract first: some hold the last payment until the deficiencies are closed or a certificate is issued.

The final bill takes the contract, with every signed change, to 100%. On a job with holdback, the holdback is still kept back from that bill, and released later on an invoice of its own:

Worked example: the last two invoices, at 10% holdback
Contract, with signed changes$200,000.00
Billed before this invoice−$185,000.00
Final progress bill$15,000.00
Less holdback, 10%−$1,500.00
Due on the final bill, before tax$13,500.00
Holdback kept on earlier bills$18,500.00
Holdback kept on the final bill$1,500.00
Holdback to release, when it’s due$20,000.00

The $20,000 is 10% of the whole contract. Bill it on its own invoice the day it’s due, so it shows up as money owed.

The holdback, released on an invoice of its own. INV-0010 keeps 10% back; INV-0030 will bill it, with its tax charged then.

Holdback is usually paid once the work is substantially complete and the time for lien claims has passed. Put the day it’s due on your calendar the day the job is done.

If it isn’t paid that day, ask in writing that day. The progress billing guide covers getting holdback released.

Check the rules where your job is

When holdback must be paid, and what has to be certified or published first, is set by lien law in your province or state and by your contract. Ask a construction lawyer before you rely on a date, and your accountant about the tax on holdback.

The warranty period, the review and the look back

Your warranty usually starts at hand-over, so write that date down. Many contracts set a year on workmanship, and some new homes carry a warranty set by law.

Book a visit before your warranty runs out. Fix what has settled or cracked, and get it signed off. It closes the warranty cleanly and reminds the client who looked after them.

Check your warranty terms

How long you warrant your work, and which new home warranty rules apply, depend on your contract and on where you build. Check both before you tell the client a date.

Ask for the review or the reference while the job is fresh, at the hand-over if it went well. Make it easy: one short message with the link, or ask if a future client may call them.

Don’t pay for a review or offer a discount for one. Many review sites don’t allow it, and a review that was paid for is worth less to the next client anyway.

Then look back. Compare what the job cost with what you estimated, while you still remember why. The job costing guide shows how.

How CrewLog does it

CrewLog has no separate deficiency list. Put each item on the job as a task, with who fixes it and a due date.

Late items have a tab of their own, and the office sees who ticked each one off.

Photograph each fix onto the job, with a note saying which item it is. Keep the manuals, warranties and as-builts in the job’s files.

On the final progress bill, choose The rest to bill what’s left of the contract. The holdback comes off it as on every progress bill, and CrewLog keeps a running total of what’s held.

Releasing it is an invoice of its own, for up to what’s held. The client opens each invoice from a link with no login.

Export the job as one folder: its daily reports, photos, documents and drawings, the reports and photos named by date. The client copy leaves out your costs, receipts and internal notes.

Mark the job Completed when it’s done. If it has a work type, its days and costs join your own averages for that kind of work.

Invoices, holdback release, photos and the job folder are on every plan, from $39 a month. Tasks and the job’s files are on Crew at $89 a month and Pro at $179. Compare the plans.

More on invoices and holdback and jobs on the features page.

More guides

All guides

Close out your next job in order.

Put every deficiency on the job as a task, bill the rest of the contract, and release the holdback on an invoice of its own.