How to estimate a construction job, step by step
Count what the drawings show, price every hour at what it costs you, and build up to a price that covers the office and leaves a profit.
An estimate is what you expect the job to cost you to build. The price comes after, once overhead, contingency and profit go on top.
Most bad estimates aren’t bad arithmetic. They’re a room nobody counted, labour priced at the wage, or a sub’s price that left half the work out.
Here’s the order experienced estimators work in, with a worked example from the first quantity to the price.
Read the drawings, then take off the quantities
Before you count anything, read the whole package: every drawing sheet, the specs, any addenda and the client’s notes. Write down the revision and date of each drawing you price from.
Then walk the site. Drawings don’t show the narrow stairs, the parking, where the bin goes or what’s behind the old drywall.
Now count, one trade at a time, in the order the job gets built:
- Measure in the unit you buy or install in. Square feet of drywall, linear feet of baseboard, each for doors and fixtures.
- Mark each item on the drawing as you count it. A highlighter on a printed set, or marks on a PDF, so nothing is counted twice or missed.
- Write down the dimensions, not only the totals. “Bedroom 2, 12 × 14 ft” lets someone else check your figure in a minute.
- Count the small things too: fasteners, adhesive, caulking and hardware. They add up on every job.
- List every question as you go. Ask it before you price, or write it down as an assumption the quote states.
An assumption you write down protects you. One you only made in your head turns into an argument about scope halfway through the job.
Price labour at what an hour really costs you
Labour is where estimates go wrong most often. Work it out in hours first, then in dollars.
For the hours, use your own past jobs: hours per sheet of drywall, per door hung, per linear foot of wall framed. Your crew’s real pace beats any figure from a book.
Where you have no history, build it from the crew and the days. Two carpenters for fifteen days at eight hours is 240 hours.
Then price each hour at its true cost: the wage plus its burden, like vacation pay, payroll contributions, workers’ comp and benefits. The job costing guide shows how.
A $36 wage with a 25% burden costs you $45 an hour. Price those 240 hours at the wage, and the estimate is $2,160 short before the job starts.
Add the hours people forget: setup and cleanup, material runs, supervision, the punch list and the callback a month later.
Add materials, equipment and subcontractors
- Materials. Price them from a supplier’s written, dated quote or your latest invoices. Add waste for cuts, breakage and pattern, and round up to full sheets, boxes and lengths.
- Equipment and rentals. The lift, the bin and the heater, by the day or the week, with delivery and pickup. Equipment you own has a cost too: give it a day rate.
- Subcontractors. Get every price in writing, then read what it leaves out. Compare two subs line by line, not total to total.
- Site costs. Permits, floor protection, a toilet, temporary power and the final clean. They belong to this job, so they go in its cost.
Waste depends on the material and the job. Tile laid on a diagonal wastes more than tile laid square. Use your own figures, and check them against what you really ordered last time.
A low sub price often has a hole in it: no permit, no cleanup, no patching after. Whatever their price leaves out, you pay for, so price the gap or ask them to include it.
Ask about tax on materials
How sales tax on the materials you buy is handled, and whether it belongs in your cost, depends on where you work and how you’re registered. Ask your accountant.
Add contingency, overhead and profit
Add those lines up and you have the direct cost: what this job takes to build. Three things go on top of it.
- Contingency, for what you can’t see yet: an old house, drawings that are thin in places. Size it to the risk, and keep it for unknowns, not for a counting mistake.
- Overhead: what isn’t tied to one job, like the office, the trucks, insurance, phones and your time at the desk. $180,000 of it on $1,500,000 of job costs a year is 12% of cost.
- Profit: what the business earns for taking the risk, on top of your own wage. Pick the figure on purpose, not whatever is left over.
Overhead and profit together are your markup on cost. If your statements show overhead as a share of revenue, that’s a margin, and the markup and margin guide shows how to convert it.
| Labour, 240 hours at $45 (wage plus burden) | $10,800.00 |
|---|---|
| Materials from the takeoff | $7,500.00 |
| Waste, 10% of materials | $750.00 |
| Equipment, rentals and the bin | $950.00 |
| Subcontractors: electrical and plumbing | $9,000.00 |
| Site costs: permit, protection, final clean | $1,000.00 |
| Direct cost | $30,000.00 |
| Contingency, 5% | $1,500.00 |
| Your cost | $31,500.00 |
| Overhead, 12% of cost | $3,780.00 |
| Profit, 8% of cost | $2,520.00 |
| Price before tax | $37,800.00 |
Overhead and profit come to $6,300: a 20% markup on your cost, and a margin of about 16.7% on the price. The figures are an example. Use your own.
Check the estimate before it becomes a quote
- Compare it with your past jobs. The example comes to $47.25 a square foot. If your last few basements ran well above or below that, find out why before you send it.
- Read the drawings once more against your takeoff. Every room, every sheet, every note. The missed item is usually on the sheet you read last.
- Have someone else look at it. A second person catches the zero you dropped and the room you skipped.
- Write down what you assumed and what you left out. Those lines go into the quote as its exclusions, as the quote guide shows.
- Keep the estimate with the job. When the job is done, compare what it cost with what you estimated, line by line. That’s how the next estimate gets better.
If the price is more than the client wants to spend, take scope out or offer a cheaper option. Cutting labour hours to make the number work only moves the loss to the end of the job.
How CrewLog does it
In CrewLog, your estimate is the quote. Each line has a type (labour, material, equipment, subcontractor, allowance or other), a quantity and unit, your cost and a markup.
Group the lines in sections if you like. Set one markup for the quote or a different one on any line, and the markup box shows the margin it gives.
Before you send it, CrewLog flags what costs money later, like no exclusions, no markup or a margin under 10%. The client only ever sees the prices.
When you win, the job opens from the quote, and its cost plan starts from the quote’s lines at your cost. Hours, receipts and signed change orders land against it as the job runs.
Give a job its work type and size, and its overview shows what your own finished jobs of that type took.
Once you’ve finished two, it shows cost and labour hours per unit, and what this job comes to at those rates. Your next estimate starts from your own numbers.