How to manage subcontractors on a construction job

Get the scope and the paperwork right before they start, hold them to their dates, and pay them the way the contract and the law say.

Field7 min readUpdated

Most jobs are built by people who don’t work for you. The electrician, the plumber and the drywall crew each run their own business, on their own schedule, with your name on the result.

Managing them well is mostly paperwork and talking, done early: a clear scope, the right certificates, dates in writing, and no surprises on either side when the bill comes.

Before they start: the scope and the paperwork

The costliest problems with subs start before they arrive: a scope nobody wrote down, or a certificate nobody checked. Both are quick to get right at the start.

A written subcontract, or at least a written scope, should say:

  • What’s included, by drawing, spec section and area, and what isn’t: who supplies the fixtures, who patches their holes, who hauls their waste.
  • The price and how it’s billed: a lump sum, unit prices or time and material, and the holdback you’ll keep.
  • The dates: when they start, how long they’ll take, and what has to be ready before they can.
  • How changes work: nothing extra is paid without a written change order, priced before the work.
  • Cleanup, protection and your site rules, so they’re part of the price, not an argument later.

Pass your own contract down. If the owner can hold you to a warranty, a notice period or closeout papers for the sub’s work, hold the sub to the same.

Then collect the paperwork before their first day on site:

  • Proof of workers’ compensation coverage, in the form your province or state uses.
  • A certificate of liability insurance, with the limits your contract asks for, and your company named on it if the contract says so.
  • Licences and trade tickets the work needs, like the electrician’s or the gas fitter’s.
  • Their safety paperwork, if your site or your client asks for it, and the name of their supervisor on site.

Write down when each one expires, and get a new one before it does. A certificate that ran out halfway through the job doesn’t cover the second half.

Workers’ comp depends on where you work

In Ontario, get a WSIB clearance certificate from each sub before they start, and a new one before it expires. Without one, you may be held responsible for premiums they owe. Other provinces and US states have their own rules. Check yours.

Coordinate their dates, and hold them to them

A sub is booked on several jobs at once, and the job that calls last gets them last. Make yours the job that called.

  1. Book the start in writing as soon as you know it, with the area and what will be ready for them.
  2. Confirm a week out, and again two days before. If the work ahead of them is late, tell them then, not the morning they arrive.
  3. Agree on their crew size. Two people on work that needs four turns a week into two.
  4. Put them on your lookahead. Their foreman confirms their dates at the weekly meeting, in front of everyone. The lookahead guide shows how.
  5. When they miss a date, write it down that day: what was promised, what happened and what it held up. Then call them.

Hold them to the schedule the way you’d want the owner to hold you: early warning, the facts in writing and a fair chance to catch up.

If it keeps happening, the subcontract’s clauses on delay and default are what you’ll rely on. Read them before you need them.

Set the site rules, and run safety for everyone

Subs work on your site, under your site rules. Go through them before the first day:

  • Where to park, where to store material and where their waste goes.
  • Working hours, noise, and anything the neighbours or the client have asked for.
  • How to protect finished work: floors, windows, the client’s house.
  • Who they report to on site, and how they tell you about a problem.

Give every new person a site orientation on their first day: the hazards, the emergency plan, the first aid kit and the muster point.

Bring their crew to your toolbox talks, and have them sign like your own. A hazard on your site doesn’t care whose payroll someone is on.

Check who is responsible for safety

Who is responsible for safety across a site, and what that means for your subs, depends on the law where you work and on your role on the job. Check the rules for your jobs.

Handle their extras and change orders

A sub’s extra is a change order one level down, and the rule is the same: price it and sign it before the work.

  1. Ask for it in writing. No extra gets paid that you didn’t approve in writing before the work started.
  2. Check it against their scope. Read the subcontract before you agree that something is extra.
  3. Find out who caused it. If the owner changed the work, the sub’s price goes into your own change order to the owner, with your markup. The extras guide shows how.
  4. Don’t commit to their price before the owner commits to yours. If the work can’t wait, get the owner’s go-ahead in writing first.
  5. Back-charge with paperwork. If a sub damages other work or leaves a mess you clean up, tell them in writing at the time, with photos and hours, before you take it off their bill.

Number their change orders and keep them with the job, beside your own, so each one points to the change it belongs to.

Pay them the way the contract and the law say

Before you pay a progress bill, check it against the work. Walk the area, and compare what they claim is done with what you see and with their schedule of values.

Then take off the holdback. Where lien law sets one, it usually applies all the way down: the owner keeps it back from you, and you keep it back from your subs.

Worked example: a sub’s progress bill
Work billed this period$20,000.00
Less holdback, 10%−$2,000.00
Pay on this bill, before tax$18,000.00

The $2,000 isn’t yours. It’s still owed to the sub, and it’s paid when their holdback is released.

Keep a running total of what you’ve kept back from each sub, the same way you track what the owner keeps back from you. The progress billing guide shows how.

Before the final payment, get what the subcontract asks for: the final invoice, warranties, closeout papers, and a statutory declaration or lien waiver where those are used.

Holdback and prompt payment rules differ

In Ontario, the Construction Act has every payer keep back 10%, and once the owner pays you, you generally have 7 days to pay your subs unless you give a notice of non-payment. Rules differ elsewhere. Ask a construction lawyer before you rely on a deadline.

How CrewLog does it

In CrewLog, each sub’s people go on the job as contacts, with their company, role, phone and email.

Keep their certificates in the job’s files, where insurance papers are sorted under Insurance. On Crew and Pro, each sub’s insurance and WSIB clearance dates go on your supplier and sub list, and CrewLog reminds you 30 days before one lapses.

A phase of a job can be marked as done by a subcontractor, with their company’s name. It shows on its week of the crew forecast and is never counted as your people.

Their crew signs your toolbox talks too. Anyone not on your team, like a sub or a visiting inspector, types their name.

In a trade meeting’s minutes, an item can go to a sub’s contact with a due date, and it carries forward to the next meeting until it’s closed.

Their invoices go on the job as Subcontractor costs, against the Subcontractors line of the job’s cost plan. On Pro, the subcontract itself goes on the job: each progress claim moves to cost, with the holdback kept back.

When their price is part of your change order, it’s a fixed line at cost, with your markup on top.

Job files, tasks, job costing, change orders and meeting minutes are on Crew at $89 a month and Pro at $179. Subcontractor phases on the crew forecast are on Pro at $179 a month, and toolbox talks on every plan, from $39 a month. Compare the plans.

More on the Schedule and job costing on the features page.

More guides

All guides

Keep every sub’s people, dates and costs with the job.

Their contacts and certificates on the job, their names on your toolbox talks, and their invoices against the job’s budget.